Inedge Power Ships 5MW/10MWh Liquid-Cooled BESS to West Africa

Recently, Inedge Power completed the production, commissioning, and factory acceptance testing of a customized liquid-cooled battery energy storage system (BESS) for a solar-plus-storage project in West Africa. The equipment has successfully passed pre-shipment inspections and is now on its way to the project site.
LFP Battery Energy Storage System

At the manufacturing facility, production teams carried out equipment assembly and quality inspections, while engineers checked system parameters, electrical configurations, and equipment interfaces. From initial technical discussions to manufacturing and testing, every stage was tailored to the project's specific requirements.

## Customized 5MW/10MWh Energy Storage Solution
Inedge Power 5MW 10MWh Liquid-Cooled Battery Energy Storage System for West Africa
The project has a planned capacity of 5MW/10MWh, consisting of two 5.016MWh liquid-cooled battery energy storage containers and one 2.5MW integrated PCS step-up unit. The new system will operate in parallel with an existing 2.5MW PCS integrated unit at the customer's site.

During the initial design phase, Inedge Power's engineering team worked closely with the customer through multiple rounds of technical discussions. Since the site already had an installed 2.5MW PCS step-up unit, the new solution needed to ensure compatibility and coordinated operation between the existing and newly supplied equipment.
BESS grid integration support
Following technical evaluation, the team developed a customized configuration integrating two 5.016MWh liquid-cooled battery containers with a new 2.5MW PCS unit. By connecting the new and existing equipment in parallel, the system forms an integrated 5MW/10MWh energy storage solution.

The electrical design adopts a single-busbar configuration. The battery containers are connected to the integrated PCS step-up unit through DC cables, and the system is then connected to the newly built 11kV central substation grid-connection switchgear through a step-up transformer.

From capacity configuration and electrical interfaces to parallel operation and grid connection architecture, the entire solution was designed around the customer's existing infrastructure, making effective use of installed equipment while meeting the project's technical requirements.
commercial microgrid energy storage
## From Engineering Design to Manufacturing and Testing

A customized energy storage solution requires more than a well-designed technical proposal. Consistent execution throughout manufacturing, system integration, and factory testing is equally important.

During production, each process was carried out according to the project's technical specifications. Engineers conducted inspections of the battery system, electrical connections, and equipment interfaces to ensure that the delivered configuration remained consistent with the approved design.

The system features lithium iron phosphate (LFP) batteries and liquid-cooling technology, with the battery containers designed for outdoor installation. In addition, considering the parallel operation of the new and existing PCS units, the engineering team addressed control coordination and communication compatibility in preparation for on-site installation and commissioning.

From engineering drawings to equipment assembly and final factory inspections, the project reflects close collaboration between Inedge Power's R&D, engineering, and manufacturing teams.
energy storage system design consultant
## Supporting Global Energy Projects with Customized BESS Solutions

Every energy storage project comes with different site conditions, grid requirements, and operational objectives. A standardized configuration may not always be the most suitable solution.

Inedge Power focuses on developing flexible, project-specific battery energy storage solutions based on customers' actual requirements. With integrated capabilities covering R&D, manufacturing, system integration, delivery, installation, commissioning, and operation and maintenance, we support customers throughout the entire project lifecycle.
energy storage operation and maintenance services
The equipment has now departed for West Africa. Once it arrives on site, Inedge Power's overseas engineering team will carry out installation, system commissioning, and grid connection activities. The team will also complete the integrated commissioning of the Energy Management System (EMS) and Battery Management System (BMS), ensuring coordinated operation across the system and supporting the project's successful commissioning.